Harrington Park Pump Station update

Since our December newsletter we have made good progress at Harrington Park Pump Station. The main focus has been on internal tasks, with electrical and cable work nearing completion, to be succeeded by HV electrical energisation and commissioning activities. Moreover, the installation of the permanent noise wall is complete, in the community favored “monument” colour has been successfully finished.

Civil works have commenced to finish the carpark and access driveways as well as landscaping at the rear of the site. Although there are remaining tasks, we anticipate completion by end May.

Landscaping plans

Planning is underway to restore this site. Once a landscaper and design is finalised we will inform the Harrington Park community accordingly.

When construction of Harrington Park Pump Station is complete, the team will leave the site until the Oran Park reservoirs are constructed. They will then return to complete the remaining commissioning activities, before bringing the station into full operation.

Share Harrington Park Pump Station update on Facebook Share Harrington Park Pump Station update on Twitter Share Harrington Park Pump Station update on Linkedin Email Harrington Park Pump Station update link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>