Preparing the area for the two new digesters
previous next
Preparing the area for the two new digesters
Preparing the area for the two new digesters
Our crew installing the steel formwork for the base of one of the two new digesters, ready for the concrete to be poured.
With the base of the digesters complete, our next step was to build the walls. The walls will be 15 metres high when finished, so we need to build them in three stages using a large tower crane.
Aerial view of our two new digesters being built.
Pouring concrete to form the walls of the new digesters.
Our two new digested completed.
Our WRRF at North Head.
Our two new digesters completed.