Prospect South to Macarthur (ProMac)

Share Prospect South to Macarthur (ProMac) on Facebook Share Prospect South to Macarthur (ProMac) on Twitter Share Prospect South to Macarthur (ProMac) on Linkedin Email Prospect South to Macarthur (ProMac) link

Under the ProMac project we are building new drinking water pipelines and infrastructure between Prospect South and Macarthur as part of Sydney Water's long-term plan to extend the city’s water capacity and supply.

ProMac will upgrade our existing water reservoirs at Liverpool, Cecil Park and Currans Hill as well as build two new reservoirs at Oran Park. This will allow for an extra 100 Megalitres of additional reservoir capacity in Western Sydney. That’s the equivalent of about 50 Olympic-sized swimming pools!

We’re also building 15 km of additional pipework, three pumping stations and upgrading our existing network to ensure growing communities in South Western Sydney have access to clean drinking water.

Sydney Water is investing in new infrastructure that will support the growing, dynamic South Western Sydney.

ProMac will help Sydney Water deliver on its vision of creating a better life with world-class water services.

Under the ProMac project we are building new drinking water pipelines and infrastructure between Prospect South and Macarthur as part of Sydney Water's long-term plan to extend the city’s water capacity and supply.

ProMac will upgrade our existing water reservoirs at Liverpool, Cecil Park and Currans Hill as well as build two new reservoirs at Oran Park. This will allow for an extra 100 Megalitres of additional reservoir capacity in Western Sydney. That’s the equivalent of about 50 Olympic-sized swimming pools!

We’re also building 15 km of additional pipework, three pumping stations and upgrading our existing network to ensure growing communities in South Western Sydney have access to clean drinking water.

Sydney Water is investing in new infrastructure that will support the growing, dynamic South Western Sydney.

ProMac will help Sydney Water deliver on its vision of creating a better life with world-class water services.

  • Currans Hill - one oversized delivery to temporarily impact parking along Turner Road, Ascot Drive and Manooka Road

    Share Currans Hill - one oversized delivery to temporarily impact parking along Turner Road, Ascot Drive and Manooka Road on Facebook Share Currans Hill - one oversized delivery to temporarily impact parking along Turner Road, Ascot Drive and Manooka Road on Twitter Share Currans Hill - one oversized delivery to temporarily impact parking along Turner Road, Ascot Drive and Manooka Road on Linkedin Email Currans Hill - one oversized delivery to temporarily impact parking along Turner Road, Ascot Drive and Manooka Road link

    Upcoming work

    We are continuing with blasting and painting of the new reservoir and are ready to install the roof. The roof sheeting will be transported in a single delivery on the back of a specialised 28 metre truck, capable of carrying roof sheets 21 metres in length.

    The delivery will occur on the morning of Tuesday 5 September 2023. Due to travel restrictions on oversized transportations, the delivery will occur at any point between 4:00am and 7:00am. The truck will park on site with the delivery until the items are ready to be unloaded during standard construction hours. The truck’s trailer will fold to a reduced size before demobilising from site on the same morning.

    This work will involve:

    • mobilising a large 28m truck through Currans Hills outside of standard work hours
    • using traffic control and a light vehicle escort along the heavy vehicle route (map overleaf)
    • placing signage and traffic cones to distinguish ‘no parking’ zones at pinch points along the heavy vehicle route in Currans Hill. Signage and cones will be placed the afternoon prior to delivery
    • door knocking properties impacted by temporary parking restrictions prior to the delivery day
    • reducing the size of the truck trailer prior to demobilising.

    Construction traffic and impacts

    There will be no road closures however delays are expected along the heavy vehicle route while the delivery is safely escorted around narrow turns. To minimise disruption to the community, we recommend avoiding this route next week between the designated delivery hours.

    Temporary ‘no parking’ signs will be positioned on the afternoon prior to delivery. Motorists and pedestrians are advised to follow all project signage and traffic control directions.

    Heavy vehicles will continue to use the route approved by Camden Council, via Turner Road, Ascot Drive and Manooka Road.

    Our standard work hours

    • 7 am to 6 pm Monday to Friday
    • 8 am to 1 pm Saturday (we are currently working extended Saturday hours until 5:00 pm for the duration of blasting and painting)
    • We will not work on Sundays or Public Holidays.

    Heavy vehicle route

  • Kemps Creek - geotechnical investigations in council road verge along Martin Road and Overett Avenue

    Share Kemps Creek - geotechnical investigations in council road verge along Martin Road and Overett Avenue on Facebook Share Kemps Creek - geotechnical investigations in council road verge along Martin Road and Overett Avenue on Twitter Share Kemps Creek - geotechnical investigations in council road verge along Martin Road and Overett Avenue on Linkedin Email Kemps Creek - geotechnical investigations in council road verge along Martin Road and Overett Avenue link

    To help inform the planning and design progression of a new drinking water pipeline, Sydney Water has engaged AECOM Australia Pty Ltd (AECOM) to undertake geotechnical investigation work in the council road verge along Overett Avenue and Martin Road in Kemps Creek.

    We will be undertaking geotechnical investigation work from Tuesday 15 August and will continue this work intermittently until the end of September 2023, weather permitting.

    This work will involve:

    • drilling boreholes in the council road verge along Martin Road and Overett Avenue
    • detecting underground services/utilities
    • excavating test pits to assess geological conditions of the area
    • carrying out topographical surveys along Martin Road and Overett Avenue
    • restoring the impacted areas.

    Construction traffic and impacts

    There will be no road closures while we undertake this work. You may experience short traffic delays while heavy vehicles navigate through the suburb. Traffic control may be on site to assist with this work.

    Our standard work hours

    • 7 am to 6 pm Monday to Friday
    • 8 am to 1 pm Saturday. We will not work on Sundays or Public Holidays.


    Location of work
    Under the ProMac project, Sydney Water will be working in several locations along the following route:

  • Currans Hill - project update and extended Saturday hours

    Share Currans Hill - project update and extended Saturday hours on Facebook Share Currans Hill - project update and extended Saturday hours on Twitter Share Currans Hill - project update and extended Saturday hours on Linkedin Email Currans Hill - project update and extended Saturday hours link

    Upcoming work

    We have completed installation of steel panels to form the new reservoir. We now need to remove the temporary coating and replace it with a permanent protective coating. This work will take 12 weeks to complete from Monday 31 July 2023, weather permitting.

    To meet critical project milestones, we will be working extended Saturday hours until 5:00 pm for the duration of this painting and blasting phase.


    Our standard work hours

    • 7 am to 6 pm Monday to Friday
    • 8 am to 1 pm Saturday (we will be working extended Saturday hours until 5 pm for the duration of this painting and blasting phase)
    • We will not work on Sundays or Public Holidays.


    This work will involve

    • delivery of specialised painting and blasting equipment
    • installation of temporary protective screens around the reservoir
    • blasting sections of the reservoir using high pressure blasting equipment early in the day
    • painting the blasted area in the afternoon.


    Construction traffic and impacts

    There will be no road closures while equipment deliveries are completed. You may experience short traffic delays while heavy vehicles navigate through the suburb outside of peak hours. Some traffic controllers may need to park in nearby streets on delivery days. Heavy vehicles will continue to use the route approved by Camden Council, via Turner Road, Ascot Drive and Manooka Road.

  • Cecil Hills - extended Saturday work hours commence from July until September 2023

    Share Cecil Hills - extended Saturday work hours commence from July until September 2023 on Facebook Share Cecil Hills - extended Saturday work hours commence from July until September 2023 on Twitter Share Cecil Hills - extended Saturday work hours commence from July until September 2023 on Linkedin Email Cecil Hills - extended Saturday work hours commence from July until September 2023 link

    As part of the Prospect to Macarthur (ProMac) program we are building a new water pumping station and new water pipelines within our Liverpool Reservoir facility to provide drinking water services for 84,000 new homes in the South West Growth Area and Western Sydney Aerotropolis Growth Area.

    The contractor has completed the installation of all civil, electrical and mechanical work at the Liverpool Reservoir site in preparation for the final stages of construction. The final stages of work will commence from Monday 10 July 2023, weather permitting.

    To meet critical project milestones, we will be working extended Saturday hours from 8 am to 5 pm from Saturday 15 July until 30 September 2023 (refer to map overleaf for location of work).

    Location of work


  • Cecil Hills and Bonnyrigg - nightwork to commence along Cowpasture Road

    Share Cecil Hills and Bonnyrigg - nightwork to commence along Cowpasture Road on Facebook Share Cecil Hills and Bonnyrigg - nightwork to commence along Cowpasture Road on Twitter Share Cecil Hills and Bonnyrigg - nightwork to commence along Cowpasture Road on Linkedin Email Cecil Hills and Bonnyrigg - nightwork to commence along Cowpasture Road link

    Construction of the new water pumping station inside the Liverpool Reservoir facility is nearly complete. We are currently completing commissioning activities to bring the facility into operation.

    As part of the work, we need to decommission the existing Bonnyrigg Water Pumping Station along Cowpasture Road, between Cecil Hills and Green Valley. This work will take 16 weeks to complete between Saturday 15 July and Monday 30 October 2023, weather permitting.

    We will notify you if there will be interruption to your water supply.


    This work will involve

    • work inside the Bonnyrigg Pump Station within standard work hours
    • excavations along council verge on the west end of Rodeo Drive within standard work hours
    • excavations parallel to Cowpasture Road outside of standard work hours at night
    • commissioning works on Rodeo Drive outside of standard work hours at night
    • installation of new electrical cables
    • restoration of all impacted areas.

    Location of work

  • Cecil Hills - night work to occur inside new pump station at Liverpool Reservoir facility, week commencing Monday 5 June 2023

    Share Cecil Hills - night work to occur inside new pump station at Liverpool Reservoir facility, week commencing Monday 5 June 2023 on Facebook Share Cecil Hills - night work to occur inside new pump station at Liverpool Reservoir facility, week commencing Monday 5 June 2023 on Twitter Share Cecil Hills - night work to occur inside new pump station at Liverpool Reservoir facility, week commencing Monday 5 June 2023 on Linkedin Email Cecil Hills - night work to occur inside new pump station at Liverpool Reservoir facility, week commencing Monday 5 June 2023 link

    As part of ProMac we are building a new water pumping station at the Liverpool Reservoir facility in Cecil Hills.

    Upcoming work

    We are currently undertaking commissioning activities to bring the new pump station into operation. As part of this work, we have been testing the newly installed pumps inside the facility. A portion of this testing will need to be completed at night between 9 pm to 7 am from Monday 5 June to Friday 9 June 2023.

    There will be minimal noise impacts and no interruptions to your water services while we complete this work.

    This work will involve

    • flushing water through newly installed pumps outside of standard work hours (refer to map overleaf for location of testing)
    • monitoring noise output
    • operating lights at the site outside of standard work hours
    • vehicle and worker movements around the site outside of standard work hours.

    Standard work hours

    • 7 am to 6 pm Monday to Friday
    • 8 am to 1 pm Saturday. We will not work on Sundays or Public Holidays.


    Location of work

  • Mount Annan - re-chlorination plant delivery outside of standard work hours, Tuesday 16 May 2023

    Share Mount Annan - re-chlorination plant delivery outside of standard work hours, Tuesday 16 May 2023 on Facebook Share Mount Annan - re-chlorination plant delivery outside of standard work hours, Tuesday 16 May 2023 on Twitter Share Mount Annan - re-chlorination plant delivery outside of standard work hours, Tuesday 16 May 2023 on Linkedin Email Mount Annan - re-chlorination plant delivery outside of standard work hours, Tuesday 16 May 2023 link

    We are building a new re-chlorination plant at our Narellan South Reservoir site at Mount Annan, to improve the management of water quality for our customers.

    Upcoming work

    The re-chlorination plant has been built off site and is now ready to be delivered in three units. A crane will arrive to site during standard work hours on Monday 15 May 2023.

    Due to busy road conditions during the day, we will need to transport the re-chlorination plant units outside of standard work hours. The units will be transported to site using three heavy vehicles on Tuesday 16 May 2023 between 2 am and 7 am, weather permitting.

    The heavy vehicles will park on site with the delivery until work can commence during our standard construction hours.

    Our standard work hours

    • 7 am to 6 pm Monday to Friday
    • 8 am to 1 pm Saturday. We will not work on Sunday or Public Holidays.

    This work will involve:

    • a crane mobilising to the site during standard construction hours
    • multiple oversized construction vehicles entering the site outside of standard construction hours
    • unloading the re-chlorination plant using a crane during standard construction hours.

    Construction traffic and impacts

    There will be an increase in construction traffic around Mount Annan during this activity (refer to map overleaf). Residents can expect to see truck and crane movements along Mount Annan Drive, Swansona Avenue, Commelina Drive, Moyengully Avenue and Indigofera Circuit (northern access route).

    Location of work


  • Oran Park/Cobbitty - extended weekend hours at Oran Park Reservoirs site, May to September 2023

    Share Oran Park/Cobbitty - extended weekend hours at Oran Park Reservoirs site, May to September 2023 on Facebook Share Oran Park/Cobbitty - extended weekend hours at Oran Park Reservoirs site, May to September 2023 on Twitter Share Oran Park/Cobbitty - extended weekend hours at Oran Park Reservoirs site, May to September 2023 on Linkedin Email Oran Park/Cobbitty - extended weekend hours at Oran Park Reservoirs site, May to September 2023 link

    As part of foundation works in preparation for construction of the new Oran Park Reservoirs, our contractor Vaughan Civil has completed site establishment and commenced concrete piling.

    Upcoming work

    Extended weekend hours will occur from Saturday 6 May 2023 until 30 September 2023 to complete piling and concrete works. Refer to map overleaf for location of work.

    As works progress, we may need to complete night work. We will notify you before this occurs.

    Extended weekend hours

    • 7 am to 6 pm Saturday and Sunday. These hours are additional to our standard work hours.

    Standard work hours

    • 7 am to 6 pm Monday to Friday
    • 8 am to 1 pm Saturday. We will not work on Public Holidays.

    Construction traffic and impacts

    Heavy vehicles will enter the site via our northern access road (off The Northern Road). Heavy vehicles will exit the site via our southern access road (off Brundson road). Refer to map overleaf.


    Location of work

  • Cecil Hills - project update, Cecil Hills Pumping Station

    Share Cecil Hills - project update, Cecil Hills Pumping Station on Facebook Share Cecil Hills - project update, Cecil Hills Pumping Station on Twitter Share Cecil Hills - project update, Cecil Hills Pumping Station on Linkedin Email Cecil Hills - project update, Cecil Hills Pumping Station link

    As part of ProMac, we are building a new water pumping station at the Liverpool Reservoir facility in Cecil Hills.

    Since our April newsletter update, we have completed pre-commissioning activities for the pumping station. This involved testing of pumps, fans and motors inside the pumping station, as well as pressure testing and disinfection of the newly installed pipe work.

    Upcoming work

    We are now ready to start commissioning activities to bring the new facility into operation. This work will be completed over 12 weeks from Monday 8 May 2023.

    This work will involve:

    • disinfecting and flushing pipework at the new pumping station facility
    • connecting the new pumping station to the live Sydney Water network
    • pumping water from the new Cecil Hills pumping station to the Bonnyrigg and Cecil Park Reservoirs intermittently throughout the day.

    Once the facility is operational, the pumps will facilitate water flow day and night, intermittently. The pumping station is lined with sound absorbing material and when commissioning is complete, a door will be installed on the pumping station to further minimise operational noise.

    What you need to know

    There will be no interruptions to your water services while we complete this work. All work associated with the new reservoir, pumping station and pipework will not affect the supply of water pressure to your property.

    Location of work


  • Cecil Hills - returning to Prince Close to complete valve replacement. No road closures.

    Share Cecil Hills - returning to Prince Close to complete valve replacement. No road closures. on Facebook Share Cecil Hills - returning to Prince Close to complete valve replacement. No road closures. on Twitter Share Cecil Hills - returning to Prince Close to complete valve replacement. No road closures. on Linkedin Email Cecil Hills - returning to Prince Close to complete valve replacement. No road closures. link

    In Cecil Hills, we installed 1.95km of new water main. As part of this work, we installed a valve in the grass verge along Prince Close in 2021 to control water flow across the Sydney Water network. In February 2023, we completed critical maintenance work on the valve. Investigation work determined that the valve will need to be replaced.

    Upcoming work

    From Monday 1 May 2023, we will return to the same location to complete a full replacement of the valve. This work will take up to two weeks to complete, followed by a further one week of testing and commissioning, weather permitting. Please see map overleaf for the location of work.

    There will be no interruptions to your driveway access or water service during this work.

    Traffic changes

    As we complete this work, traffic control will be used to assist with the management of traffic, however no road closures are planned along Prince Close. A small crew of workers will park on the grass verge off the corner of Prince Close and Sandringham Drive. Refer to map for location of parking.


    Thank you for your cooperation and patience during this essential work.

    Location of work

Page last updated: 29 Apr 2024, 03:09 PM