Our Projects in Bayside Council

Share Our Projects in Bayside Council on Facebook Share Our Projects in Bayside Council on Twitter Share Our Projects in Bayside Council on Linkedin Email Our Projects in Bayside Council link

We're working in these suburbs, click below to find out more.

Arncliffe, Banksia, Bardwell Park, Bardwell Valley, Bexley, Bexley North, Botany, Brighton-Le-Sands, Carlton (part), Daceyville, Eastgardens, Eastlakes, Hillsdale, Kingsgrove (part), Kogarah (part), Mascot, Rockdale, Rosebery (part), Turrella and Wolli Creek.

For more information

We’re here to help! You can always contact us during normal business hours on Delivering4Customers@sydneywater.com.au or 1800 006 113 and select option 2. If we are unable to answer, or if you are calling outside normal business hours, leave a detailed message and we'll get back to you as soon as possible or the next business day.

We're working in these suburbs, click below to find out more.

Arncliffe, Banksia, Bardwell Park, Bardwell Valley, Bexley, Bexley North, Botany, Brighton-Le-Sands, Carlton (part), Daceyville, Eastgardens, Eastlakes, Hillsdale, Kingsgrove (part), Kogarah (part), Mascot, Rockdale, Rosebery (part), Turrella and Wolli Creek.

For more information

We’re here to help! You can always contact us during normal business hours on Delivering4Customers@sydneywater.com.au or 1800 006 113 and select option 2. If we are unable to answer, or if you are calling outside normal business hours, leave a detailed message and we'll get back to you as soon as possible or the next business day.

  • Arncliffe 2205

    Share Arncliffe 2205 on Facebook Share Arncliffe 2205 on Twitter Share Arncliffe 2205 on Linkedin Email Arncliffe 2205 link

    Northern Georges River Submain - Wastewater Upgrade

    Project timing: May 2024 to August 2025

    We’re upgrading 3 km section of a large wastewater main knows as the Northern Georges River Submain. This system services the community from Fairfield to Arncliffe. Our work will increase the capacity within the tunnel, improving its function and reliability of your wastewater service.

    Most of our work is underground, however we will have four major sites set up above ground for access into the wastewater system and desilting activities.

    Work involves:

    Site establishment and traffic management

    • four major sites and four minor sites will be set up in suburbs Arncliffe, Rockdale and Kogarah

    Desilting (removing silt and debris from within the system)

    • We expect to remove a total of approximately 1360 tonnes from the asset
    • we will be desilting from Vincents Avenue, Rockdale and Subway Road, Rockdale
    • there will be changes to local traffic and increased truck movements for deliveries and the disposal of silt and debris.

    Tunnel Repairs

    • cleaning and surface preparation
    • removal and replacement of internal structures (ladders, step irons within the wastewater tunnel
    • core hole drilling and final inspection.

    Restoration

    • Once the above work is finished, all sites will be disestablished and impacted areas will be restored. All restoration works will be performed in accordance with Council and Traffic NSW requirements.

    Work hours: 7 am to 6 pm, Monday to Friday. 8 am to 1 pm Saturdays (if required) No work is planned for Sunday or public holidays.

    Click here to read the community newsletter for more detailed information.

  • Rockdale 2216

    Share Rockdale 2216 on Facebook Share Rockdale 2216 on Twitter Share Rockdale 2216 on Linkedin Email Rockdale 2216 link

    Northern Georges River Submain - Wastewater Upgrade

    Project timing: May 2024 to August 2025

    We’re upgrading 3 km section of a large wastewater main knows as the Northern Georges River Submain. This system services the community from Fairfield to Arncliffe. Our work will increase the capacity within the tunnel, improving its function and reliability of your wastewater service.

    Most of our work is underground, however we will have four major sites set up above ground for access into the wastewater system and desilting activities.

    Work involves:

    Site establishment and traffic management

    • four major sites and four minor sites will be set up in suburbs Arncliffe, Rockdale and Kogarah

    Desilting (removing silt and debris from within the system)

    • We expect to remove a total of approximately 1360 tonnes from the asset
    • we will be desilting from Vincents Avenue, Rockdale and Subway Road, Rockdale
    • there will be changes to local traffic and increased truck movements for deliveries and the disposal of silt and debris.

    Tunnel Repairs

    • cleaning and surface preparation
    • removal and replacement of internal structures (ladders, step irons within the wastewater tunnel
    • core hole drilling and final inspection.

    Restoration

    • Once the above work is finished, all sites will be disestablished and impacted areas will be restored. All restoration works will be performed in accordance with Council and Traffic NSW requirements.

    Work hours: 7 am to 6 pm, Monday to Friday. 8 am to 1 pm Saturdays (if required) No work is planned for Sunday or public holidays.

    Click here to read the community newsletter for more detailed information.

  • Mascot 2020

    Share Mascot 2020 on Facebook Share Mascot 2020 on Twitter Share Mascot 2020 on Linkedin Email Mascot 2020 link

    Wastewater Upgrade - Coward Street Mascot

    153 Coward Street to 206 Coward Street, Mascot

    Click here to view the community newsletter

    We are upgrading large wastewater pipe along Coward Street, Mascot.

    We have completed the investigations along Coward St in preparation for construction in mid-2023. Before we start, we are going to be demolishing and old, vacant building within the Sydney Water pump station at 153 Coward Street. This project will significantly reduce the risk of wastewater overflows

    Project timing: 28 August 2023 to November/December 2023.

    UPDATE: Demobilisation has been delayed. This was due to a fault noticed in the sewer junction connection points. The supplier has been called to site to assess and repair the issue. We had to stop work restoring the road and reconnecting the live sewer as there was high risk of wastewater overflow.

    08 MARCH 2024: We have removed the fencing from Aloha Street - normal traffic has returned to this area. We plan to disestablish the west end compound near O'Riordan Street in mid-April 2024. We apologise for the delay at this end of Coward Street.

    Update: On Friday 8 December 2023, we'll begin the pack down of traffic control and site compound near Aloha STreet/Coward Street. Two way traffic is expected to start back on Tuesday 12 December 2023.

    Update: Night work, weekend work and extended hours

    We have now reached a critical stage in our project (stage 4 - see below) where we need work as quickly as possible to prevent the underground pit in which the pipe is being placed, from collapsing. This means we will be working earlier than usual, at night and across certain weekends in October 2023. We know this isn’t ideal, but we will do our best to minimise noise and impacts.

    Please see the calendar below for the schedule of work:

    Click here to view the community update about extended working hours in October 2023

    Community contact: 1800 006 113 (option 2) If you call outside of work hours, please leave a return phone number.

    Construction work involves:

    • Stage 1: site establishment and set up of HDD rig entry pit on the road in front of 151 Coward Street
    • Stage 2: drilling underground from 151 Coward Street through to 206 Coward Street
    • Stage 3: site establishment and set up HDD rig exit pit on the road in front of 206 Coward Street
    • Stage 4: welding and installing the new pipe
    • Stage 5: restoration of roadway and all impacted areas.

    What you need to know:

    We will be drilling underground using a Horizontal Directional Drill (HDD) rig. This will be set up on the road along the alignment of the wastewater pipe. Traffic will be changed temporarily to allow for two way traffic movement while we work.

    Our machinery can be noisy and our set up will disrupt usual traffic while were on the road - we have all mitigation measures in place to ensure we minimise impacts on the community and complete the project as quick as we can.

    For regular updates, email delivering4customers@sydneywater.com.au with your name and suburb.

    You can also visit this page again to see how the work is progressing.


    Mascot Wastewater Pumping Station Mechanical & Electrical Upgrade

    6 Coleman Street, Mascot

    We are upgrading the Mascot wastewater pumping station.

    Construction activities will include:

    • replacing internal infrastructure such as pumps, ventilation system, valves and pipes

    • improving access to equipment within the pumping station

    • upgrading the existing above ground infrastructure

    • restoring areas impacted by our work.

    Some of this work needs to be done at night due to wastewater flow levels. We know this is not ideal, but we’ll do everything we can to keep noise to a minimum.

    Work hours: 7 am to 6 pm, Monday to Friday. 8 am to 1 pm Saturdays (if required) No work planned on Public Holidays.

    Night work hours: 7 pm to 5 am

    Start: June 2021 Finish: This work is currently on hold.




  • Kogarah 2217

    Share Kogarah 2217 on Facebook Share Kogarah 2217 on Twitter Share Kogarah 2217 on Linkedin Email Kogarah 2217 link

    Northern Georges River Submain - Wastewater Upgrade

    Project timing: May 2024 to August 2025

    We’re upgrading 3 km section of a large wastewater main knows as the Northern Georges River Submain. This system services the community from Fairfield to Arncliffe. Our work will increase the capacity within the tunnel, improving its function and reliability of your wastewater service.

    Most of our work is underground, however we will have four major sites set up above ground for access into the wastewater system and desilting activities.

    Work involves:

    Site establishment and traffic management

    • four major sites and four minor sites will be set up in suburbs Arncliffe, Rockdale and Kogarah
    • The site in Kogarah is located on Gladstone Avenue - you will notice a temporary change to the pedestrian walkway around the compound area - for your safety please follow the traffic and pedestrian signs.

    Desilting (removing silt and debris from within the system)

    • We expect to remove a total of approximately 1360 tonnes from the asset
    • we will be desilting from Vincents Avenue, Rockdale and Subway Road, Rockdale
    • there will be changes to local traffic and increased truck movements for deliveries and the disposal of silt and debris.

    Tunnel Repairs

    • cleaning and surface preparation
    • removal and replacement of internal structures (ladders, step irons within the wastewater tunnel
    • core hole drilling and final inspection.

    Restoration

    • Once the above work is finished, all sites will be disestablished and impacted areas will be restored. All restoration works will be performed in accordance with Council and Traffic NSW requirements.

    Work hours: 7 am to 6 pm, Monday to Friday. 8 am to 1 pm Saturdays (if required) No work is planned for Sunday or public holidays.

    Click here to read the community newsletter for more detailed information.