We’re working in Wallis Street
From Monday, 11 to Tuesday, 12 September we will be excavating launch pits on Wallis Street. High noise activities are required including saw cutting and excavating the road.
Once the launch pits are complete, we will commence slip lining where we insert the new pipe into the existing water main. This is expected to occur from Monday, 18 September to Thursday 21 September.