Dapto 2530
Gentles Avenue
We're currently relining the internal walls of the larger reservoir at Dapto, and replacing the roof.
Construction started in March 2022. Despite several unexpected delays, we expect to finish the project by the second quarter 2024.
3 January 2024 update.
Prince Edward Drive
We're upgrading about 195 metres of the existing water main in Prince Edward Street, Dapto.
Work started on 30 January 2023 and have temporarily finished work for now. We have some more investigation work to do, refer to the below update. After we’ve assessed the information from the investigation work and designed the upgrade for the remaining section of water main that needs to be replaced, we’ll return later in the year to do this work. We’ll write to adjacent property owners again before starting that work.
4 December 2023 update.
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends